Arthon Industries Limited
General Contracting & Aggregate Production
 

Bailey Road
Okanagan Highway No. 97 - Intersection Improvements

Commencement : May, 2011.

Improving the Safety of Travellers in the Okanagan.

Arthon was awarded the contract to complete intersection improvements starting May 2011, completion by July 2011.

To be advised by E-Mail on updates for this project, please send an email to BaileyRoad@arthon.com to be put on our notification list.

Arthon's key individuals who will run and complete this project :
  • Mr. Nick Rodger, EIT, Superintendent
  • Mr. Graham Bennison GSC / Mr. Guy Ferrari, Project Managers
  • Mr. Steve Dimond, GSC, M.Sc., P.Eng. - Quality Control, Traffic, Safety & Administration

Project Information & Updates

  1. Road Closure Information
    • First Closure was Wed. May 18th - 10 minutes only.
    • The allowable Closure period is generally up to 30 minutes between 9 am and noon. (some differences for Sat. and summer periods)
  2. Photo Gallery


Southbound View - on Highway 97 at Bailey Road (pre-improvements)
Bailey Road - South view.... on Highway #97
Northbound View - on Highway 97 at Bailey Road (pre-improvements)
Bailey Road - South view.... on Highway #97