Project Overview Airphoto
Blast Movies
View the Operations
|
 |
 |

|
Arthon Contractors Inc.
General Contracting & Aggregate Production
OKANAGAN HIGHWAY No.97 - BENTLEY ROAD TO OKANAGAN LAKE PARK LKI Segment 1115, KM 31.565 to KM 38.545
(6.980) GRADING AND PAVING
Commencement : February, 2008.
Four lane roadworks and 1,000,000 m3 rock removal and 800,000 m3 dirt removal over a 7 km section of BC's main north-south highway corridor.
The B.C. Ministry of Transportation awarded Arthon Contractors Inc. a $38.6 MM contract to complete roadway construction by summer 2009.
***************************************************************************
Arthon is the GOLD Sponsor :
NO HWY 97 CLOSURES : 4pm to 10pm on Fri. Nov. 28 ... just the odd minor delay.
Summerland's 21st Annual FESTIVAL OF LIGHTS (new window)
Come Join the Fun on Friday, Nov. 28, 2008 @ 4:30 p.m.
A Community Party : Celtic Entertainment by KINSHIP, Fireworks, Food - On MAIN Street - closed to traffic.
Click for Photos of 2007 event ...
***************************************************************************
Arthon's key individuals who will run and complete this project :
- Mr. Graham Bennison, GSC, Project Manager
- Mr. Guy Ferrari, Project Management and Chief Superintendent
- Ms. Jacqui Lloyd, Project Public Information Officer
- Mr. Steve Dimond, GSC, M.Sc., P.Eng., Quality Control, Traffic, Safety & Administration
Project Information & Updates
(look for more information here as project continues)
Highway Cameras ... Click Image for NEW Window
Then click a date for the image at that time .....
At "La Punta Norte" B & B
|
At the Goat Bluff
|
CLICK TO ENLARGE - PROFILE of Cuts (red) and Fills (green) over 7km project... (Back button to return - Note; Vertically exaggerated... )
| |
 |
 |
 |