OKANAGAN HIGHWAY No.97 -
BENTLEY ROAD TO OKANAGAN LAKE PARK
LKI Segment 1115, KM 31.565 to KM 38.545
(6.980) GRADING AND PAVING

Commencement : February, 2008.

ROAD CLOSURE INFORMATION

Updated April 25, 2008


 
(As emailed to the Update list ... join by sending email to Summerland @ arthon.com
*****************************************************************
Greetings

In the following week, Monday May 5 through Saturday May 10, 
Highway 97 road closures north of Summerland will continue to 
include a half hour closure a 10:00 a.m. and a 1 HOUR closure 
at 1:00 p.m. each weekday.  

These closure times often are for a shorter period and may not, 
in fact, occur at all, depending on drilling production on that 
day.  However, we ask that the traveling public plan for the full 
closure during the times posted.

Minor stops for truck crossings of the highway can be anticipated 
anytime from 7:00 a.m. through to 5:00 p.m.... generally 30 seconds 
or less.

PLEASE NOTE :

THE HIGHWAY IS NOW A DESIGNATED 70 km/hr CONSTRUCTION SPEED ZONE.


30 MINUTE closure :

Mon May 5 --> Sat May 10  @ 10:00 am  (Sunday EXCLUDED)


1 HOUR closure :

Mon May 5 --> Sat May 10  @ 1:00 pm  (Sun EXCLUDED)


Thank you for your continued patience.  Please obey flaggers and
reduce speeds through the Construction Zone .... our flaggers do
appreciate a smile and a wave :-)


Cheers
Jacqui Lloyd
Arthon


Please visit www.arthon.com for updates.

Send an email to Summerland@arthon.com to join this list
 or for removals from the list (please indicate "removal" if so)

***************************************************************
***************************************************************
Hello folks,

Currently, the project is using only one shift  . . . a day shift. 
Starting Sunday May 11 OR alternately Monday May 19, 2008 a night shift 
is scheduled to be added. Which date depends on the project's progress 
next  week.

How will this affect you?

The following are night-time closures allowances:

    30 Minute Closure allowances :
    9:00 pm to 12:30am (anytime during that period)
 
    1 HOUR Closure allowances :
 
    7:00 pm to 8:00 pm
    8:30 pm to 9:30 pm
    10:00 pm to 11:00 pm
 
    2 HOUR closures allowances
 
    12:30 AM to 2:30 AM (ie late night, early morning)
    3:00 AM to 5:00 AM
 
    5 minute delays allowed throughout the night shift ...

Next week I will update you about which of these windows will be 
used and when the night shift will start.

Cheers,

Jacqui Lloyd



*****************************************************************
Prior Closure Information :

Back to Summerland Main
 
To be advised by E-Mail on updates for this project, please send an email to summerland@arthon.com to be put on our notification list.
Arthon Construction Ltd.
PO Box 29001,
Okanagan Mission
Kelowna, British Columbia
Canada, V1W 4A7
Tel: (250) 494-8766
Fax: (250) 764-6143
Email Arthon

 
Arthon Construction Ltd.  (250) 764-6144    www.arthon.com