OKANAGAN HIGHWAY No.97 -
BENTLEY ROAD TO OKANAGAN LAKE PARK
GRADING AND PAVING

Commencement : February, 2008.

Rock Blasting Examples - April 24, 2008

(477K bytes file size)
See also Blasting on April 17, 2008. These files are still photos animated, not video. You require QUICKTIME to view... see www.apple.com/quicktime/ for free download.
 
  • Blast Location: STATION 131+16 to 131+36
  • Blast Size: 2,650 m3
  • Distance of Blast to Goat Bluff: 1.516 km
  • Time of Blast: 2:41 Pm
  • Impact: Dust on Road, very minor rock on road
  • Traffic Stopped 2:39 to 2:46: Pm (7 minutes)
  • Seismic vibration at Goat Bluff (sta. 114+50): No recording from monitor
  • Acoustic noise level at Goat Bluff (sta. 114+50): No recording from monitor
  • Goats movement: 1 Goat present on north side of bluff. Stopped grazing and looked in direction of blast.

Back to Summerland Main
 

Arthon Construction Ltd.
PO Box 29001,
Okanagan Mission
Kelowna, British Columbia
Canada, V1W 4A7
Tel: (250) 764-6144
Fax: (250) 764-6143
Email Arthon

 
Arthon Construction Ltd.  (250) 764-6144    www.arthon.com