OKANAGAN HIGHWAY No.97 -
BENTLEY ROAD TO OKANAGAN LAKE PARK
GRADING AND PAVING

Commencement : February, 2008.

Rock Blasting - Wednesday, July 09, 2008
2nd Major Extended Delay

Blast Location - July 08, 2008

Danger Rock
Today, July 08, 2008, we had a blast which resulted in remaining danger rock. This rock had the potential of coming down onto the highway and required an extended closure to safely secure the area. The last occurance where an extended delay occurred due to "blast danger rock" was on April 17, 2008. Arthon is blasting between 1 and 4 times daily.
 

The photos show the overhanging rock above the highway. We flagged across this rock to ensure safe passage conditions and were able to remove the rock by about 8:25 pm during the 7pm closure. This meant an extended closure but resulted in safe conditions for travel. These events are unplanned, and do not happen often, but must be dealt with when they occur.
 
We thank the travelling public for their patience and understanding .... moving 1.8 Million cubic metres of material will result in these situations on occasion ... and they are fortunately rare.
 
See the blast in a animated photo sequence below. It is a large file... please wait until it loads... you will require Quicktime for the animation movie to work.

 

 
(1.3M bytes file size - movie below)
See also Blasting on April 17, 2008.
See also Blasting on April 23, 2008.